Third Party Access

We are promoting Third-Party Access to our gas infrastructure as part of our commitment towards supporting the opening up of the domestic gas market. 


AVAILABLE CAPACITY AT REGASIFICATION TERMINAL SUNGAI UDANG, MELAKA, MALAYSIA

The Subscribed Capacity made available for transfer from Capacity User pursuant to Access Arrangement ("AA") for Regasification Terminal Sungai Udang and the information provided in AA 26.7(a):

TermCapacity
0600 hours on 1st January 2021 to 0600 hours on 1st January 2023 up to 105,205.4792 MMBtu per day

Important Notes:

  1. Any interested licensed Applicant(s) may apply for the Subscribed Capacity up to 105,205.4792 MMBtu per day and must be for the full Term as described above.
  2. The Access Request Form for the available Subscribed Capacity must be completed, submitted to pgb.marketing@petronas.com, and received by Operator no later than 2359 hours on 31st July 2020. 
  3. The completed Access Request Form will be processed, and the available capacity will be allocated by the Operator on a “first come, first served” basis as per AA 3.3(c).
  4. Any successful licensed Applicant(s) is required to undertake the Partial Service Transfer processes as prescribed in AA 26.6, and enter into a Terminal Use Agreement with Operator.

Access Arrangement:

PENINSULAR GAS PIPELINE RGT SG UDANG RGT PENGERANG

Tariffs under the Third Party Access (TPA) System for:

  • Peninsular Gas Utilisation (PGU)
  • Regasificaton Terminal Sg Udang (RGTSU) in Melaka
  • Regasification Terminal Pengerang (RGTP) in Johor

 

The Tariffs for Pilot Regulatory Period (PRP) for year 2019 from 1 January until 31 December for the following facilities under PGB Group of Companies, are as follows:

 

Gas Facilities

Pilot Regulatory Period (PRP)

Year 2019

PGURM1.072/GJ/Day
RGTSURM3.518/mmbtu/Day
RGTP

USD0.637/mmbtu/Day

 

Effective 1 January 2020, the tariffs for Regulatory Period 1 (RP1) for period from 1 January 2020 until 31 December 2022 for the following facilities under PGB Group of Companies, are as follows:

 

Gas Facilities

Regulatory Period 1 (RP1)

Year 2020-2022

PGU
RM1.129/GJ/Day
RGTSURM3.455/GJ/Day
RGTP

RM3.485/GJ/Day

 *System Correctional Charges (SCC) is not applicable for 2020