1 March Hand over of Centralised Utility Facilities Project site from Vinyl Chloride Malaysia (VCM) to PGB
3 March Initial piling work to mark the first physical activity at CUF project site in Kerteh
28 May Handing-over to the Co-Generation license for the Centralised Utility Facilities (CUF) project
9 September PGB received to the Grand Award from the Malaysian Society of Occupational Safety & Health (MSOSH)]
1 December PGB received the National Annual Corparate Report Award (NACRA) for Exellence Award under the Industrial Product category
19 December Signing of Contract for the Procurement, Construction and Comissioning of Natural Gas Pipelines; The Supply, Coating, Delivery, and Storage of Pipe; and The Supply and Delivery of Ball Valves and Actuators for the Peninsular Gas Uitilisation Loop 2 Project |